2013 Projects

Malaysia First Multi-Span UHPDC Pedestrian/Motorcycle/Ambulance Crossing, Kuala Sepetang, Perak.

51

Project: To Construct a Pedestrian & Motorcycle Bridge from Kuala Sepetang Town to Kampung Seberang, Kuala Sepetang, Larut, Matang & Selama District, Perak D.R.

(Membina Jejantas Pejalan Kaki dan Motosikal Dari Pekan Kuala Sepetang Ke Kg. Seberang Di Kuala Sepetang, Daerah Larut, Matang Dan Selama, Perak D.R. (N/PK/155/2012))

Structure Type: 106m crossing over Sg. Sangga Besar

Superstructure Feature: 1 piece of DURA® UTG1200-20m pedestrian-motorcycle bridges and 2 pieces of DURA® UTG1200-22.5m pedestrian-motorcycle ramps.

Substructure Feature: 600mm diameter spun pile (Grade80) to an estimated length of 60m

Client: JKR Perak   JKR          Consultant: Jurutera Perunding Prima Reka Sdn Bhd   prima reka

Contractor: Jujur Peransang Sdn Bhd (Class C)                        

Commence Date:
02 July 2012                 Complete Date: 18 November 2013

Contract Period: 72 Weeks

Status: Completed

Project signboard.
Original site for the proposed pedestrian bridge from Pekan Kuala Sepetang to Kg. Seberang (09/09/2011).
A busy weekday where the river is full of fishing boats.
Most commonly fishing boats used by local villagers.
For the last five decades, villagers using small boat to cross the river to the other site of the village.
Small boat crossing is dangerous and not convinient to the villagers.
Bicycle is the major mode of transportation at Kg. Seberang.
Some houses of the villagers.
JKR Officer Mr Ong having discussion with JD Salahuddin and other land officers.
A humble chinese street at Kg Sepetang.
Limited space for site storage.
Demolition work in progress (04/09/2012).
Demolition of shop for construction of abutment A (25/09/2012).
Demolition of houses for construction of abutment B (25/09/2012).
Piling equipments and spun piles on a pontoon ready for piling works.
Piling work in progress (24/10/2012).
Completion of piling work.
Reinforcement for pier cap 2.
Pier cap 2 concreted with grade80 concrete (09/01/2013).
Concreting pier cap 3 in progress (11/01/2013).
Concreting pier cap 3 in progress (11/01/2013).
Transporting Grade80 concrete using a small pontoon.
Lifting concrete up to the pier cap.
Lifting concrete up to the pier cap.
Grade80 reinforced concrete pier cap 3.
A picture taken from the top of the pier cap showing houses at both sides of the river.
DURA UHPdC customised U trough pedestrian girder (05/03/2011).
DURA UHPdC customised U trough pedestrian girder (05/03/2011).
After flip up side down (23/03/2013).
PT work in progress (16/05/2013).
Substructures.
Uploading precast beam using 2 units 20 tonnes capacity mobile crane (29/06/2013).
Uploading precast beam using 2 units 20 tonnes capacity mobile crane (29/06/2013).
Beam ready for transportation (29/06/2013).
Lorries arrived to Lumut Port early of the morning (30/06/2013).
A unit of 200 tonnes crawler crane used to lift the DURA beam to pontoon.
1st beam loaded onto the pontoon.
3rd beam loaded onto the pontoon.
Three beams loaded (30/06/2013).
Lifting of DURA beam (10/07/2013).
Lifting of DURA beam (10/07/2013).
Two spans launched.
Three spans completed (10/07/2013).
Elevation view of Kg Sepetang bridge.
Inside deck view.
Installation of roofing in progress.
The completed Kuala Sepetang bridge.
The completed Kuala Sepetang bridge.
Kuala Sepetang bridge.
Kuala Sepetang bridge.
Kuala Sepetang bridge.
Kuala Sepetang bridge.