2013 Projects

Perak First Multi-Span DURA Bridge, Lenggong, Perak

panaroma final

Project:
Naiktaraf Jalan & Jambantan di Sg. Nerok, Kota Tampan Air (Muaran), Jalan Lenggong, Gerik, Hulu Perak, Perak D.R.

(To Upgrade the Road and Bridge at Sungai Nerok, Kota tampan Air (Muaran), Jalan Lenggong, Gerik, Hulu Perak District, Perak D.R.)

Structure Type: Three spans 30m long by 15m wide UHPdC integral beam-deck system crossing Sg. Nerok. (Total 90m long)

Superstructure Feature: 30 pieces of DURA® TBG1325-29.5m and 36 pieces DURA® SRWS2520

Substructure Feature:  600mm diameter spun piles

Loading Type: Full HA+45HB Highway loading (BD37/01)

Client: JKR Perak   JKR         
Consultant: Jurutera Perunding Warisan / TS Yee & Associate          Warisan logo   TS Yee logo

Contractor: Shazeme Enterprise

Contract Period: 18 months

Status: Completed

Original site, Tasek Rapan a peaceful country side which full of Malaysia flavour.
Project sign board.
Original bailey bridge crossing the river, badly rusted after decades in service.
Poor condition of existing bridge.
Repair and replacement of new timber decking in every 2 years.
Piling work in progress.
Post-tensiong of Dura bridge beams in progressed.
Uploading TBG1325-29.5 beam to the pole trailer (25/09/2012).
Fasterning the beam.
A unit 160 tonnes crane used for unloading of beams.
Arrival of DURA beams to the job site (26/09/2012).
Arrival of pole trailer to the storage yard (26/09/2012).
Unloading beam.
Storage yard of the beams.
Substructures (24/05/2013).
The intermediate span (28/08/2013).
Completion of beam launching for intermediate span (28/08/2013).
Completion of beam launching for 2nd span (30/08/2013).
External span at abutment B (30/08/2013)
Launching of third span at abutment A (31/08/2013).
Completion of beam launching for 3rd span (31/08/2013).
Stitching of joint (11/09/2013).
Completiong of stitching work (28/10/2013).
Completiong of stitching work (28/10/2013).
Completion of RC parapet (27/11/2013).
Completion of RC parapet (27/11/2013).
Completion of bridge work (06/12/2013).
Premix laid (14/12/2013).
Sg Nerok Bridge (06/02/2014).
Sg Nerok Bridge (06/02/2014).
Sg Nerok Bridge (06/02/2014).
Original site, Tasek Rapan a peaceful country side which full of Malaysia flavour.
01/31 