Single Span UHPC Bridge at Ulu Lawin, Perak


Project: To Construct Bridge at Ulu Lawin, Daerah Hulu Perak, Gerik, Perak Darul Ridzuan.


 (Membina Jambatan Ulu Lawin, Daerah Hulu Perak, Gerik, Perak Darul Ridzuan).

 GPS Location: 5.300921 N; 101.052175 E 

Structure Type: Single Span UHPC Beam Composite In Situ Deck Bridge System : 18m x 4m wide.

Superstructure Feature: 3 piece of DURA® IB650-18m with Cast In-Situ RC Deck

Substructure Feature: 2 nos. of cast in-situ RC abutments

Foundation Feature: 200mm x 200mm RC pile.

Loading Type: HA+KEL or 30 units HB loadings

Client: Pejabat Daerah Dan Tanah, Hulu Perak, Gerik Perak

S.O.: Jurutera Daerah , JKR Daerah Perak JKR

Consultant
: Jurutera Perunding Concrete Technology

Contractor: FD Construction and Supplier

Contract Period: : 3 Months

Construction Status: Completed
Sg Lawin.
RC square pile used as foundation.
RC piles installed.
Construction of RC abutments.
Abutments done and ready for beam launching.
Transportation of Dura I-beam to site and ready for beam launching (110618).
Three I-beams launched on to abutments.
Installation of left-in formwork onto DURA I-beams.
Construction of In-situ RC decking (060918).
Completion of Ulu Lawin bridge(021018).
Completion of Ulu Lawin bridge(021018).
Completion of Ulu Lawin bridge(021018).
Completion of Ulu Lawin bridge(021018).
Completion of Ulu Lawin bridge(021018).
Sg Lawin.