2019 Projects

A Single Span 55m DURA Bridge Crossing Sg. Buloh at Alam Perdana Mega Development

Project: Proposed Construction And Completion of Bridge Entrance Access Road and River Widening For Development of 439 Acres Land At Alam Perdana Mukim Ijok Daerah Kuala Selangor, Selangor Darul Ehsan

(Cadangan Membina Jambatan Jalan Masuk Untuk Pembangunan 439 Acres Tanah Di Alam Perdana Mukim Ijok, Daerah Kuala Selangor)

GPS Location: 3.263539 N; 101.457634 E

Structure Type: Single Spans 55m by 22.4m Wide (Left & Right) Composite Bridge System.

Superstructure Feature: 6 pieces of DURA® UBG2000-55m with Cast In-Situ RC Deck

Substructure Feature: Cast in-situ RC abutments

Foundation Feature: 600mm dia. Spun pile (Class B)

Loading Type: HA+ 45 units HB loadings (BD37/01)
Client: Menteri Besar Incorporated Selangor Pemerbadanan (MBI) Logo mbi
S.O.: Worldwide Property Management Sdn Bhd

Consultant
: JPCT / Zar Perunding

Contractor: Unisima Construction Sdn Bhd

Contract Period: 12 Months

Construction Status: Completed       

Bridge site at Sg. Buloh.
Piling workn in progress (240419).
Unloading beam for assembly (020519).
Six number of UBG2000-55m assembled at site.
PT work in progress (010819).
PT work in progress (010819).
Preparation for beam launching by Asiagroup (080819).
Preparation for beam launching (080819).
Launching first beam (090819).
Lifting of first beam (090819).
Six beams launched (100819).
All beam launched (100819).
Preparation for consturction of RC deck (240819).
Facade and precast parapet installed.
Complete bridge with wearing surface laid.
Completed bridge.
Completed bridge.
Completed bridge.
Bridge site at Sg. Buloh.
01/18 
start stop bwd fwd

First Dura Footbridge in China

Project: Extension and Reconstruction of Huadu Avenue (North Approach Junction of Airport to Cotton Tree Drive)

花都大道(机场北进路口至红棉大道段)扩建改造工程

GPS Location: 23.435640 N; 113.301292 E

Structure Type:
Double Span 30m by 5.3m wide Double T-UHPC Bridge Girder

Superstructure Feature: 2 pieces of Double Tee- Integral Beam-Deck Bridge

Substructure Feature: Cast in-situ RC piers

Foundation Feature: 1m dia. Bored piles

Loading Type: 5 kPa

Client:    广州市花都区地方公路管理站 Guangzhou Huada District Local Highway Management Station

Consultant
: 广州市公路勘察设计有限公司  Guangzhou Highway Survey and design Co. Ltd

Contractor: 广东华隧建设集团股份有限公司   Guangdong Hua Tunnel Construction Group Co. Ltd

Construction Status: Completed       

General arrangement of Huadu footbridge.
Typical Cross section view .
Batching of UHPC at the casting yard.
Casting of Zhonglu-Dura UHPC footbridge.
Typical cross section.
Full span 30m T beam casted in one shoot.
Match casting for second beam (210319).
Match casting with visitors (210319)
Dura double T footbridge (060419).
Air curing of the beam with plastic sheet used to cover the beam.
Steam curing of the beam.
Briefing for installation team prior to beam launching.
Parking of two units 260 tonnes mobile cranes (070819).
Lifting of the first double-T girder.
Lifting of the first double-T girder.
Positioning of the first ZhongLu-Dura double T girder using 2 units 260t mobile cranes (070619).
First girder installed (070619).
Lifting of the second double-T girder.
Two girders successfully installed.
The completed first ZhungLu-Dura Footbidge at Huadu.
Huadu Footbridge using UHPC material.
Completed bridge.
General arrangement of Huadu footbridge.
01/22 
start stop bwd fwd


Small Contribution for the Local Contractor on Lahat Bridge 2, Mukim Hulu Kinta Single Spans

Project: To Construct Bridge at Government Land Lot 35781 For Proposed Skim Perindustrian Fasa 1, Mukim Hulu Kinta, Daerah Kinta, Perak Darul Ridzuan (Bridge 2)

 (Cadangan Kerjatanah Bagi Cadangan Skim Perindustrian Fasa 1 Di Atas Tanah Kerajaan Sebahagian Lot 35781, Mukim Hulu Kinta, Daerah Kinta, Perak)

 GPS Location: 4.524624 N; 101.045489 E

Structure Type: Single Spans 12m by 30m Wide (Left & Right) Composite Bridge System.

Superstructure Feature: 15 pieces of DURA® IB650-12m with Cast In-Situ RC Deck

Substructure Feature: Cast in-situ RC abutments

Foundation Feature: 200 x 200mm dia. SQ RC. pile (Class B)

Loading Type: HA+ 30 units HB loadings (BD37/01)

Client: Priority Focus Sdb Bhd

S.O.: Priority Focus Sdb Bhd

Consultant: JPCT

Contractor: Mutual Way Civil Works Sdn Bhd

Contract Period:

Construction Status: Completed       

Original site view of Lahat Bridge 2
Beam launching in progress (230319).
Beam launching.
RC deck casted.
Completed bridge.
Original site view of Lahat Bridge 2
1/5 
start stop bwd fwd


Lahat Bridge 1, Mukim Hulu Kinta Single Spans

Project: To Construct Bridge at Government Land Lot 35781 For Proposed Skim Perindustrian Fasa 1, Mukim Hulu Kinta, Daerah Kinta, Perak Darul Ridzuan (Bridge 1)

(Cadangan Kerjatanah Bagi Cadangan Skim Perindustrian Fasa 1 Di Atas Tanah Kerajaan Sebahagian Lot 35781, Mukim Hulu Kinta, Daerah Kinta, Perak)

 GPS Location: 4.525349 N; 101.041652 E

Structure Type: Single Spans 13.5m by 20m Wide (Left & Right) Composite Bridge System.

Superstructure Feature
: 11 pieces of DURA® IB650-13.5m with Cast In-Situ RC Deck

Substructure Feature: Cast in-situ RC abutments

Foundation Feature: 200 x 200mm dia. SQ RC. pile (Class B)

Loading Type: HA+ 30 units HB loadings (BD37/01)

Client: Priority Focus Sdn Bhd

S.O.: Priority Focus Sdn Bhd

Consultant: JPCT

Contractor: Mutual Way Civil Works Sdn Bhd

Contract Period:

Construction Status: Under Construction
Original site view for Lahat Bridge 1
Beam launching
Position of the I-beams
Position of the I-beams
Beam and formwork fully installed
Completed bridge.
Completed bridge.
Original site view for Lahat Bridge 1
1/7 
start stop bwd fwd


Another 35m Single Span DURA bridge Crossing Sungai Pinji at Ipoh


Project: To Replace Bridge at Sungai Pinji FT 3150/2/4 Bridge Sungai Pinji, Kinta, Perak Darul Ridzuan.


(Projek Menggantikan Jambatan FT 3150/2/4 Jambatan Sungai Pinji, Daerah Kinta, Perak Darul Ridzuan)

GPS Location: 4.530863 N; 101.071710 E

Structure Type: Single Spans 35m by 17m Wide Composite Bridge System.

Superstructure Feature: 4 pieces of DURA® UBG1250-35m with Cast In-Situ G40 RC Deck

Substructure Feature: Cast in-situ RC abutments

Foundation Feature: 300mm dia. Micropiles

Loading Type: HA+ 45 units HB loadings (BD37/01)

Client: Kementerian Kerja Raya Malaysia    KKr

S.O.: Jabatan Kerya Raya Kinta JKR

Consultant: Perunding HJRS

Contractor: ZA (Malaysia) Sdn Bhd

Contract Period: 18 months

Construction Status: Completed

Project signboard.
Construction site with temporary bailey bridge installed.
Construction site with temporary bailey bridge installed.
Construction site with temporary bailey bridge installed (031118).
New bridge site at Sungai Pinji.
Construction of micropiles at abutment A in progress (250119).
Driling of 300mm dia. hole.
Abutments completed (230619).
Four UBG1250-35m ready for beam launching.
Lifting of beam on to prime mover (290619).
Transporting beam for beam launching.
Lifting the last beam for positioning.
All four beam positioned as per drawing.
All four beam seated (290619).
Completed Kg Pinji bridge open for traffic.
Completed Kg Pinji bridge open for traffic.
Completed Kg Pinji bridge open for traffic.
Project signboard.
01/17 
start stop bwd fwd


© 2009-2020 by GPIUTMD