Dura Pile Firstly Used in Canada, Lily River Detour Bridge

Project Title: Highway 11, Lily River Detour Bridge Near Kapuskasing, Ontario, Canada.

GPS Location: 49.4121111 N, -82.428639 W

Product: 6 Nos. of DURA® UHPC H-piles (Length = 9 m)

Client: Ontario Ministry of Transportation

Superintendent
Officer.: LEA Consulting

Consultant: LEA Consulting

Contractor/designer: Facca Incorporated

Contract Period: 12 months

Construction Status: Completed Summer 2020

Casting of Dura H-pile.
Pretension strands used in the UHPC pile.
Moulding of the piles.
First Dura 9m long pretension H-pile (come with pile shoe).
Dura piles.
Driving of DURA pile in progress.
Dura piles after driven.
Casting of Dura H-pile.
1/7 
start stop bwd fwd

Replacement of 57 Years Old Bridge at Sungai Guntung, Setiu


Project:  To Construct Bridge at Sungai Guntung, FT003/619/50, Setiu, Terengganu.


(Menggantikan Jambatan Sungai Guntung, FT003/619/50, Setiu, Terengganu)

GPS Location: 5.58656 N; 102.70621 E

Structure Type: Single Span 65m by 14m Wide Composite Bridge System.

Superstructure Feature: 3 pieces of DURA® UBG2500-65m with Cast In-Situ RC Deck

Substructure Feature: Cast in-situ RC abutments 

Foundation Feature: 300mm dia. Micro Pile.

Loading Type: SV100 loadings (BS EN 1991-2-2003)

Client: Jabatan Kerja Raya Malaysia JKR                S.O.: JKR Daerah Setiu JKR

Consultant: Primareka Consultants  prima reka

Contractor: Dura Construction Sdn Bhd  4 DURA Construction 2

Contract Period: 24 months

Construction Status: Completed

Project Signboard
Existing Sg. Guntung bridge built in 1961.
Existing Sg. Guntung bridge built in 1961.
Sg Guntung Bridge at FT003-619-50.
Piling in progress
Micropiling for abutment A.
Prepartion of lean concrete at the pile cap.
Pushing cable and bearing blocks installation (250519).
Stressing bottom tendons.
Stressing top tendon.
Excessive strands at anchor block cut.
Patching of anchor blocks.
Grouting of tendons (250519).
Abutments completed and ready to received beams (290719).
Abutments completed and ready to received beams (290719).
UBG2500-65m ready for beam launching (290719).
Upload beams for launching (040819).
Transporting 1st beam for launching (050819).
Positioning 1st beam (050819).
Getting ready to lift second beam (050819).
Lifting 2nd beam.
Positioning 2nd beam (050819).
Toing last third beam for launching (050819).
Construction of in-situ deck.
RC deck partially constructed.
Completion of RC deck construction.