Staff Login



2019 Projects

Replacement of 57 Years Old Bridge Project at Sungai Raia, Kinta


Project: To Construct Bridge at Sungai Raia, FT001/583/20, Kinta, Perak.

 
(Menggantikan Jambatan Sungai Raia, FT001/583/20, Kinta, Perak)

GPS Location: 4.51582 N; 101.13747 E

Structure Type: Single Span 50m by 11m Wide Composite Bridge System.

Superstructure Feature: 3 pieces of DURA® UBG1750-50m with Cast In-Situ RC Deck

Substructure Feature: Cast in-situ RC abutments

Foundation Feature: 300mm dia. Micro Pile.

Loading Type: SV100 loadings (BS EN 1991-2-2003)

Client: Jabatan Kerja Raya Malaysia   JKR                 S.O.: JKR Daerah Kinta JKR

Consultant: Primareka Consultants  prima reka                  Contractor: Dura Construction Sdn Bhd  4 DURA Construction 2

Contract Period
: 24 months

Construction Status
: Completed

Project signboard for Sg. Raia Bridge
Existing Sg Raia Bridge.
Existing old bridge.
Micropiles used as foundation.
Maintain load testing in progress.
Construction of micropiles at abutment B completed (011018).
Lifing of DURA IB650-24m for the utility beams (141018).
Two numbers of DURA-IB650 was positioned.
Installation of precast DURA thin plank.
Two beams and precast DURA planks fully installed in half day.
Hacking of the existing old bridge (221018).
Hacking work in progress (221018).
Lifting of the first U-beam.
Assembly of UBG1750 segments.
Assembly of UBG1750 segments.
In-situ RC deck slab constructed.
Apporach slab constructed.
Approach road soon will be ready.
Sg Raia bridge temporary open for traffic (280519).
Sg Raia bridge temporary open for traffic (280519).
Project signboard for Sg. Raia Bridge
01/20 
start stop bwd fwd


Five Spans UHPC Composite Bridge from Kg. Seberang Manong to Pekan Manong


Project: To Construct Bridge at Sungai Perak from Kg. Seberang Manong to Pekan Manong (Kampung Simpang Melembu), Kuala Kangsar, Perak Darul Ridzuan


(Membina Jambatan Menyeberang Sungai Perak di antara Kampung Seberang Manong ke Pekan Manong (Kampung Simpang Melembu), Kuala Kangsar, Perak Darul Ridzuan)

GPS Location: 4.598792N; 100.881463E

Structure Type: Five Spans UHPC Beam Composite In Situ Deck Bridge System: 45m + 70m + 70m + 70m + 45m x 11.5m wide.

Superstructure Feature: 9 pieces of DURA® UBG3000-70m and 6 pieces of DURA® UBG2250-45m with Cast In-Situ RC Deck

Substructure Feature: Cast in-situ RC abutments

Foundation Feature: 1500mm dia. Bored Piles

Loading Type: LM1 + LM3 SV80

Client: JKR Malaysia JKR                            S.O.: JKR Perak  JKR 

Designer: JKR Malaysia  JKR

Contractor: Kumpulan Awambina Sdn Bhd

Contract Period: 24 months

Construction Status: Completed

Original site
The bridge project site crossing to Sungai Perak.
Construction of temporary platform in prgress.
Temporary bridge
Temporary bridge under installation
Abutment A.
Pier 1.
Pier 2 under construction.
Installation of launching platform in progress.
First DURA UBG3000-70m.
Post-tensiong mock up on the UBG3000-70m.
Full mockup on post-tensioning work of DURA UBG3000-70m.
Unload and assembly of first DURA UBG2250 segment.
Unloading and assembly of U segments.
Installation of strands.
External tendons and ducting.
JD JPR Muar witnessing the progress work during beam launching (160918).
Cutting of extra strands after PT.
Tendons installed and post-tensioned.
Prepation of temporary staging for UBG3000-70m beam assembly.
Prepation of temporary staging for UBG3000-70m beam assembly (280918).
Unloading UBG3000 segment (261018).
Unloading more UBG3000 segments.
90 tonnes capacity crawler crane used for unloading and assembly of segments.
Temporary platform for UBG3000-70m assembly.
Temporary platform.
Assembly of UBG3000-70m segments (071118).
Assembly of UBG3000.
Temporary tie rods tensioning used to temporary connect the segments.
Assembly and PT work in progress on UBG3000-70m for span 2 (171118).
Assembly and PT work in progress on UBG3000-70m for span 2 (171118).
Assembly and PT work in progress on UBG3000-70m for span 2 (171118).
Assembly and PT work in progress on UBG3000-70m for span 2 (171118).
PT top tendons (171118).
Stressing in progress (191118).
Completion of PT work for first beam.
Direct beam launching of span 1, UBG2250-45m (240119).
Beam launching of UBG2250-45m for span 1.
Direct launching using 2 units 200 tonnes mobile cranes.
Completed RC decking for span 1 (080519).
Lifting of UBG2250-45m for last span (130619).
Completion of beam launching for the last 5th spans.
Installation of precast parapet (140819).
Demantling of steel temporary bridge (280919).
Manong bridge soon will be completed and open to traffic (201019).
Manong bridge soon will be completed and open to traffic (201019).
Original site
01/46 
start stop bwd fwd


Replacement Bridge at Kg. Bagan Lawin using Single Spans

Project: To Replace A Collapse Bridge at Kampung Bagan Lawin, Daerah Hulu Perak, Perak

(Cadangan Membina Jambatan Kampung Bagan Lawin, Daerah Hulu Perak, Perak)

GPS Location: 5.292316 N; 101.061059 E

Structure Type
: Single Spans UHPC Beam Composite in-situ Deck Bridge System: 13m x 4.5m wide.

Superstructure Feature
: 2 pieces of DURA® IB650-13m with Cast In-Situ RC Deck

Substructure Feature: 2 nos. of Cast in-situ RC abutments

Foundation Feature: 200mm & 200mm RC Pile

Loading Type: HA+KEL or 30 units HB loadings

Client: Jabatan Tanah Gerik

S.O.: Jabatan Tanah Gerik

Consultant: JPCT

Contractor: MAE Equity

Contract Period: 3 months

Construction Status: Completed       

RC piles installed.
Access road to the bridge (061119).
Beam and UHPC left-in formwork fully installed.
Installation of dura UHPC railing
Completed bridge
Completed bridge
Completed bridge
Completed bridge
RC piles installed.
1/8 
start stop bwd fwd


Replacement Bridge of Air Lembu, Perak using Single Spans

Project: To Replace A Collapse Bridge Air Lembu, Kampung Padang Kunyit, Daerah Hulu Perak, Perak

(Cadangan Membina Jambatan Air Lembu, Kampung Padang Kunyit, Daerah Hulu Perak, Perak)

GPS Location: 5.405915 N; 101.129767 E

Structure Type: Single Spans UHPC Beam Composite In Situ Deck Bridge System: 13m x 4.5m wide.

Superstructure Feature: 2 pieces of DURA® IB650-13m with Cast In-Situ RC Deck

Substructure Feature: 2 nos. of Cast in-situ RC abutments

Foundation Feature: 200mm & 200mm RC Pile

Loading Type: HA+KEL or 30 units HB loadings

Client: Jabatan Tanah Gerik

S.O.: Jabatan Tanah Gerik

Consultant: JPCT

Contractor: Mutiara Mae Sdn Bhd 

Contract Period: 3 months

Construction Status: Completed


Substructures ready to receveid beams (300919).
Two I-Beams launched (181019).
UHPC left-in formwork used at the middle portion of the slab.
RC deck fully casted.
Completed bridge.
Completed bridge.
Completed bridge.
Completed bridge.
Substructures ready to receveid beams (300919).
1/8 
start stop bwd fwd

A Single Span 55m DURA Bridge Crossing Sg. Buloh at Alam Perdana Mega Development

Project: Proposed Construction And Completion of Bridge Entrance Access Road and River Widening For Development of 439 Acres Land At Alam Perdana Mukim Ijok Daerah Kuala Selangor, Selangor Darul Ehsan

(Cadangan Membina Jambatan Jalan Masuk Untuk Pembangunan 439 Acres Tanah Di Alam Perdana Mukim Ijok, Daerah Kuala Selangor)

GPS Location: 3.263539 N; 101.457634 E

Structure Type: Single Spans 55m by 22.4m Wide (Left & Right) Composite Bridge System.

Superstructure Feature: 6 pieces of DURA® UBG2000-55m with Cast In-Situ RC Deck

Substructure Feature: Cast in-situ RC abutments

Foundation Feature: 600mm dia. Spun pile (Class B)

Loading Type: HA+ 45 units HB loadings (BD37/01)
Client: Menteri Besar Incorporated Selangor Pemerbadanan (MBI) Logo mbi
S.O.: Worldwide Property Management Sdn Bhd

Consultant
: JPCT / Zar Perunding

Contractor: Unisima Construction Sdn Bhd

Contract Period: 12 Months

Construction Status: Completed       

Bridge site at Sg. Buloh.
Piling workn in progress (240419).
Unloading beam for assembly (020519).
Six number of UBG2000-55m assembled at site.
PT work in progress (010819).
PT work in progress (010819).
Preparation for beam launching by Asiagroup (080819).
Preparation for beam launching (080819).
Launching first beam (090819).
Lifting of first beam (090819).
Six beams launched (100819).
All beam launched (100819).
Preparation for consturction of RC deck (240819).
Facade and precast parapet installed.
Complete bridge with wearing surface laid.
Completed bridge.
Completed bridge.
Completed bridge.
Bridge site at Sg. Buloh.
01/18 
start stop bwd fwd

© 2009-2020 by GPIUTMD