Project
: Menaiktaraf Jalan Dari Kok Lanas Ke Sek. Banggol Saman Ke Sek. Danang, Kereteh, Pasir Putih, Kelantan. Fasa 2. (Bridge 1)

GPS Location: 5.920296N, 102.28407E

Structure Type: Single span 25m long x 12m wide DURA composite bridge.

Superstructure Feature: 2 pieces of DURA UBG1750-25m

Substructure Feature: Cast in-situ RC abutments

Foundation Feature: 500mm dia. PC Spun Pile (Grade80, Class B)

Loading Type: Full HA + KEL & 45 units HB loadings

Client: KKLW    Logo KKLW

Consultant: M Zah Perunding

Contractor: Jemmings Sdn Bhd

Contract Period: 24 months

Status: Completed

Access road to the proposed bridge site.
Kok Lanas bridge 1 site.
Concreting of substructure.
Concreting of substructure.
2 pieces of DURA UBG1750-25m arrived at site.
2 pieces of DURA UBG1750-25m arrived at site.
Post tensioning is done on 25m Dura UBG 1750 at site.
Partially complete abutment is ready for beam launching.
Concreting in-situ RC deck.
RC deck continuous with abutments.
Abutment and wingwall.
Installation of precast parapet.
Installation of precast parapet.
Parapet constructed.
Access road to the proposed bridge site.
01/14 