Project
: Flood Mitigation Plan at Bertam Valley Cameron Highlands, Pahang. Project in Widening & Deepening Bertam River & Other Related Works  - Bridge MDCH 1, 2 & 3.

(Rancangan Tebatan Banjir Lembah Bertam Cameron Highlands, Pahang. Project Melebar Dan Mendalamkan Sungai Bertam Dan Kerja-Kerja Berkaitan - Bridge MDCH1, 2 and 3)

Nos. of Bridges: 3

GPS Location
: 4.417252N, 101.397668 E (MDCH Bridge 1); 4.416551N, 101.398419 E (MDCH Bridge 2); 4.416410N, 101.399668 E (MDCH Bridge 3)

Structure Type: Single span 30m long x 10.5m wide DURA composite bridge

Superstructure Feature: 3 pieces of DURA® UBG1250-30.0m per bridge

Substructure Feature: Cast in-situ RC abutments

Foundation Feature: 300mm dia. micropiles

Loading Type: Combination of HA + KEL & 30 units HB loadings (BD37/01)

Client: JPS Malaysia    jps

S.O.: JPS Cameron

Consultant: Jurutera Perunding Concrete Technology (Alternative Design)

Contractor: Jutabina Sempurna Sdn Bhd / Maltecon Builder Sdn. Bhd.

Contract Period: 12 months

Construction Status: Completed
Existing Sungai Bertam, Cameron Highland.
Existing bridge of MDCH Bridge 1 site.
MDCH2: Lifting of first end segment of UBG1250 (10/10/2015).
MDCH2: Lifting of second intermediate segment of UBG1250 (10/10/2015).
MDCH2: Two segments aligned on the temporary supports.
MDCH2: A single span UBG1250-30m come with three segments fully assembled (10/10/2015).
MDCH2: Elevation view of a newly assembled UBG1250-30m (10/10/2015).
PT tendon and anchorage plates installed.
Stressing of bottom tendon of UBG1250-30m.
Three U beams post-tensioned and detached from temporary intermediate supports.
Grouting of tendons in progress.
Three U beam PT and hogged.
Three U beams post-tensioned and detached from temporary intermediate supports.
Preparing formwork for RC decking (10/11/2015).
Reinforcement of RC deck (10/11/2015).
In-situ RC deck completed (30/01/2016).
Completed bridge MDCH2.
Completed bridge MDCH3.
Completed Sungai Bertam MDCH bridges.
Completed Sungai Bertam MDCH bridges.
Completed after 1 year.
Completed after 1 year.
Completed after 1 year.
Completed after 1 year.
Completed after 1 year.
Completed after 1 year.
Completed after 1 year.
Existing Sungai Bertam, Cameron Highland.
01/27 