ZhungLu-DURA Bridge Used Reconstruction Project in Guangdong, China (溪东桥)

Project: Guangdong Old Bridge Reconstruction Project(广东省旧桥改造项目) Part 1

GPS Location: 23.995425 N; 116.818768 E

Structure Type:
Three spans simply supported 16m by 7.5m wide UHPC composite bridge system

Superstructure Feature: Six (6) pieces per span of precast/prestress UHPC I-beam composited with reinforced NSC deck

Substructure Feature: Cast in-situ RC piers

Foundation Feature

Loading Type: First class load of highway 公路桥涵设计通用规范 (JTG D60-2015)

Client:    广东省基础工程集团有限公司 (Guangdong Foundation Engineering Group Co, Ltd.)

Consultant: 中铁二院工程集团有限责任公司 (CREC, China Railway Engineering Corporation)

Contractor: 广东华隧建设集团股份有限公司     Guangdong Hua Tunnel Construction Group Co. Ltd

Construction Status: Under Construction       

Casting of ZL-DURA beams.
Stressing work in progress for ZL-DURA I-beams.
Grouting of tendons.
Ready for steam curing for the beams.
Launching of beams.
Launching of beams (050120).
Casting of ZL-DURA beams.