Replacing Jambatan Buloh using UHPFRC Accelerate Bridge Construction (ABC) Method

Project: To Replace Buloh Bridge FT005/476/70, Kuala Selangor, Selangor Darul Ehsan

(Menggantikan Jambatan Buloh, FT005/476/70, Kuala Selangor, Selangor Darul Ehsan)

GPS Location: 3.313171 N; 101.277764 E

Structure Type
: Single Spans UHPFRC Beam Composite In Situ Deck Bridge System: 15.55m x 22m wide.

Superstructure Feature
: 14 pieces of DURA® IB650 – 15.55m with Precast RC Deck Stitch with In-situ UHPFRC

Substructure Feature: 2 nos. of Existing Cast in-situ RC abutments

Foundation Feature:

Loading Type: HA+KEL or 45 units HB loadings

Client: Kementerian Kerja Raya

S.O.: JKR Daerah Kuala Selangor   JKR

Consultant: JKR Malaysia   JKR

Contractor: Jaticon Sdn Bhd

Contract Period: 12 Months

Construction Status: Under Construction
First half of the extsing bridge dismantle.
Existign bridge abutment.
Casting of in-situ RC deck.
Four beams casted.
Site ready for beam launching.
Four beams launched overnight.
Preparation of UHPC stitching joint.
Deck connection prior castign of UHPC stitches.
Aggregate exposed at the connection jointing.
Engineers inspection before concreting.
Soffit view of the beams.
Side view of the bridge.
Portable shear mixer used for the production of UHPC.
Mixing of on-site UHPC.
Laying of UHPC.
Curong compound apply on the expose surface of the fresh UHPC.
A thin plastic layer used to cover the fresh UHPC stitching.
First half of the extsing bridge dismantle.