Malaysia Vision Valley (MVV) Road Bridge from Nilai-Labu to Bandar Enstek

Project: Construction And Completion of Bridge No. 5 at Sg. Jijan And Other Associated Works for Malaysia Vision Valley (MVV) – Membina Jalan Baru Dari Nilai – Labu Ke Bandar Enstek, Daerah Seremban, Negeri Sembilan

(Cadangan Membina Jambatan No. 5 Di Sungai Jijan – Membina Jalan Baru Dari Nilai – Labu Ke Bandar Enstek, Daerah Seremban, Negeri Sembilan)

GPS Location: 2.714865 N; 101.790573 E

Structure Type: Single Spans 33m by 25m Wide (Left & Right) Composite Bridge System.

Superstructure Feature: 6 pieces of DURA® UBG1500-33m with Cast In-Situ RC Deck

Substructure Feature: Cast in-situ RC abutments

Foundation Feature: 600mm dia. Spun pile (Class B)

Loading Type: HA+ 45 units HB loadings (BD37/01)

Client: JKR Malaysia  JKR

S.O.: JKR      JKR

Consultant: Khairi Consult Sdn Bhd

Contractor: Dura Construction Sdn Bhd

Contract Period: 10 Months

Construction Status: Under Construction       

Sg Jijian bridge site.
Sg Jijian bridge site.
Spun pile used as foundation.
Spun pile used as foundation.
Unloading of beam segment. (210120).
Assembling of beam segments.
Three beams aligned.
Sg Jijian bridge site.
1/7 
start stop bwd fwd
contentmap_plugin

© 2009-2020 by GPIUTMD