Staff Login



China Foot Bridge 2 - Double Span 30m

Project: Extension and Reconstruction of Huadu Avenue (North Approach Junction of Airport to Cotton Tree Drive)

花都大道(机场北进路口至红棉大道段)扩建改造工程K11+915

GPS Location: 23.434114°E, 113.210209°N

Structure Type: Double Span 30m by 5.3m wide Double T-UHPC Bridge Girder

Superstructure Feature
: 2 pieces of Double Tee-Integral Beam-Deck Bridge

Substructure Feature
: Cast in-situ RC piers

Foundation Feature
: 1m dia. Bored piles

Loading Type
: 5 kPa

Client
:    广州市花都区地方公路管理站Guangzhou Huada District Local Highway Management Station

Consultant: 广州市公路勘察设计有限公司Guangzhou Highway Survey and design Co. Ltd

Contractor: 广东华隧建设集团股份有限公司Guangdong Hua Tunnel Construction Group Co. Ltd

Construction Status: Under Construction
A 30m long double T beam yet to be post-tensioned.
30m long double T beam.
A 30m long double T beam yet to be post-tensioned.
30m long double T beam.
A 30m long double T beam yet to be post-tensioned.
1/2 
start stop bwd fwd


MALAYSIA BOLEH !!! - Dura Bridge Made from Malaysia Going to be Used in India


Project: Construction of Major Bridge across Sole Nalla on Latur – Nitur -  Nilanga – Balki – Road NH72K.


GPS Location: 18.256878N, 76.724448E

Structure Type
: 2 spans x 55.5 m long (total 111 m), Major Bridge across Sole Nalla

Superstructure Feature: Simply Supported Four (4) UHPC Box Girders for each span

Substructure Feature: RC Portal Piers

Foundation Feature: Eight (8) Drilled Piles for Each Foundation.

Loading Type: IRC Class Loadings.

Client: Maharashtra State Road Development Corporation.

S.O.: Valecha-SDPL JV, Áyoleeza Consultants Pvt. Ltd.

Consultant: Technology and Proof Consultant: Indian Institute of Technology (IIT), Bombay 

                     Indian Consultant: Shirish Patel and Associates      
                    
                     Malaysian Consultant: HSS Engineers  Sdn. Bhd.                       
Contractor: Shinde Developers Pvt. Ltd. logo shinde
Contract Period: 1 Years

Construction Status: On-going
Construction of foundation work in progress.
Drop- in hammer used to dig holes on the ground.
Installation of steel cage into the dug holes.
Steel cage installed.
Preparation of bore pile starter bars (160519).
Preparation of bore pile starter bars at the pier region (160519).
Construction of Abutment A
Construction of foundation work in progress.
1/7 
start stop bwd fwd


The Application of 60m Long DURA U Bridge at Hulu Besut

Project: To Construct A New Bridge From Kg. Pasir Akar To Kg. Durian Telor, Hulu Besut, Terengganu

(Projek Membina Jambatan Baru Dari Kg. Pasir Akar Ke Kg. Durian Telor, Hulu Besut, Terengganu)

 GPS Location: 5.639662 N; 102.499176 E

Structure Type: Three Spans UHPC Beam Composite In Situ Deck Bridge System: 40m + 60m +40m x 11.5m wide.

Superstructure Feature
: 3 pieces of DURA® UBG2500-60m with Cast In-Situ RC Deck

Substructure Feature: Cast in-situ RC abutments

Foundation Feature: 800mm & 1000mm Diameter Bored Pile

Loading Type: BD 37/01 – HA+30HB & HA+45HB

Client: JKR Malaysia  JKR

S.O.: JKR Malaysia  JKR

Consultant
: JKR Malaysia  JKR

Contractor: SS Base Contractors Sdn Bhd

Contract Period: 24 months

Construction Status: Under Construction       

Project signboard (130219).
Current bridge site (130219).
Current bridge site with temporary bridge installed (130219).
Construction of abutment (130219).
Piling work in progress (130219).
Splicing and aligning beams
Precast DURA UBG3000-60m beam aligned near job site.
Project signboard (130219).
1/7 
start stop bwd fwd

© 2009-2020 by GPIUTMD