DURA First Contribution for DBKL on 49m Long Bridge at Jalan Jelatek

Project: Replacement Of The Old Concrete Bridge To New Concrete Bridge Crossing Klang River at Jalan Jelatek, Kuala Lumpur.
            
(Cadangan menggantikan jambatan konkrit sediaada kepada jambatan baru merentasi sungai kelang, di Jalan Jelatek , Kuala Lumpur.)

GPS Location: 3.1648208 N; 101.7347227 E

Structure Type: Single Span 49m by 29.15m (Avg.) Wide Composite Bridge System.

Superstructure Feature: 11 pieces of DURA® UBG1500-49m with Cast In-Situ RC Deck

Substructure Feature: Cast in-situ RC piers

Foundation Feature: N/A

Loading Type: HA+ 45 units HB loadings (BD37/01)

Client: Dewan Bandaraya Kuala Lumpur (DBKL)

S.O.: Dewan Bandaraya Kuala Lumpur (DBKL)

Consultant: Ranhill Consulting Sdn Bhd.

Contractor: Umech Construction Sdn Bhd

Contract Period: 2 years 6 months

Construction Status: Under Construction       

Project signboard and detail.
Existing bridge in Jalan Jelatek.
Underneath view of the existing old brige.
Project signboard and detail.
1/3 
start stop bwd fwd


Single Span New Assembly Hall Majlis Perbandaran Manjung


Project: To Construct a New Assembly Hall for Majlis Perbandaran Manjung


(Cadangan Membina Dewan Bahuru Majlis Perbandaran Manjung Untuk Majlis Perbandaran Manjung)

GPS Location: 4.195326 N; 100.663248 E

Structure Type: Single Spans 30m Cross Beam

Superstructure Feature: 1 pieces of DURA® TBeam1325-30m

Substructure Feature: Cast in-situ RC Column

Foundation Feature: RC Pile 200 x 200

Loading Type: Building Imposed Load of 5 kPa
Client: Majlis Perbandaran Manjung  majlis perbandaran manjung
S.O.: Yang Dipertua, Majlis Perbandaran Manjung

Consultant: Pusaka  Runding Sdn  Bhd 

Contractor: Hayyan Iktiqad Sdn Bhd 

Contract Period: 12 Months

Construction Status: Under Construction
Manjung assembly hall (231018).
Arrival of DURA TBG1325 segment.
Unloading TBG segment.
Assembly of TBG1325-30m for PT work.
Assembly of TBG1325-30m for PT work.
Stressing of DURA TBG1325-30m beams by PSC Freysinet (231018).
2 units 200 tonnes mobile cranes are used to launched the 30m beams (291018)
Lifting of the beam
Lifting of TBG1325-30m using two mobile cranes
Lifting of TBG1325-30m using two mobile cranes
Project signboard.
Construction of secondary RC beam in progress (040219).
Close-up view after removal of timber prop.
Elevation view of the Dura beam used as transfer beam for a stadium.
DURA T-Beam used as transfer beam.
Manjung assembly hall (231018).
01/15 
start stop bwd fwd

New Extension and Widening of Batu Kawan Bridge 1 using Dura


Project: New Extension and Widening of Road Bridge of Sungai Jawi  (Bridge 1) 
             
(Pelebaran Jambatan Batu Kawan Sediada Merentasi Sungai Jejawi Di Batu Kawan Seberang Perai Selatan, Pulau Pinang.)

GPS Location: 5.2651550, N; 100.4390400 E

Structure Type: Multiple Span 211m by 40m Wide Composite Bridge System.

Superstructure Feature: 24 pieces of DURA® UBG1500-43.5m and 16 pieces of DURA® UBG1500-37.25m with Cast In-Situ RC Deck

Substructure Feature: Cast in-situ RC piers

Foundation Feature: Spun Pile 450mm

Loading Type: HA+ KEL & 45 units HB loadings (BD37/01)

Client: Penang Development Corporation (PDC)

S
.O.: Jabatan Kerja Raya (JKR)  JKR

Consultant: M.E.I Consultants Sdn Bhd.

Contractor: Zibina Jaya Sdn Bhd

Contract Period:

Construction Status: Under Construction
Existing concrete bridge crossing Sungai Jawi.
Exisiting bridge.
Existing bridge.
Soffit view of existing bridge.
Existing concrete bridge.
Transporting of U segments to site.
Unloading of U-segment.
Align beam segments.
14 beams assembled.
14 beams aligned.
14 beams aligned.
Post tensioning work in progress (290918).
All beams fully grouted into the ducts.
Spun pile used as foundation.
Abutment A.
Pier 1.
Construction of substructures on going.
Substructure work in progress.
Existing concrete bridge crossing Sungai Jawi.